First phase of Malaysia's East Coast Rail Link set to open with 16 stations and fares from RM60
20 October 2026
Malaysia Rail Link Sdn Bhd (MRL) chief executive officer Darwis Abdul Razak said on 20 October 2026 that the first phase of the East Coast Rail Link (ECRL) may open on 12 December 2026, or earlier if final testing proceeds smoothly.
Phase 1 has 16 stations, from Gombak in Selangor to Kota Baru in Kelantan, passing Temerloh, Kuantan Port City, Dungun and Kuala Terengganu.
A fault-free run begins on 23 October 2026 and trial operations are planned for November 2026.
The Cabinet approved the fare structure on 16 October 2026. One-way Transit fares start at RM60 for Gombak to KotaSAS, RM95 to Kuala Terengganu and RM125 to Kota Baru; Express fares to Kota Baru start at RM147.
The Transit service stops at all 16 stations and takes nearly five hours to Kota Baru, while the Express stops only at KotaSAS and Kuala Terengganu and completes the journey in four hours.
Cargo operations are slated to start in 2028 and are expected to provide 70 per cent of initial revenue.
In plain words
ECRL East Coast Rail Link — A railway being built across Peninsular Malaysia linking the east coast states to the Klang Valley.
MRL Malaysia Rail Link Sdn Bhd — The government-owned company that develops and owns the East Coast Rail Link.